Planning a Renovation? Here’s How Long It Really Takes with an Interior Designer
- Interior Artist Pte Ltd
- May 30
- 3 min read

Understanding the Renovation Timeline: What to Expect When Hiring an Interior Designer
Embarking on a home renovation journey in Singapore is an exciting milestone—but understanding the renovation timeline is crucial for a stress-free experience. Many homeowners underestimate the planning and preparation required before any actual work begins. When you engage a professional interior designer in Singapore, the home renovation process is broken into clearly defined stages, each playing a vital role in delivering a cohesive and high-quality transformation. This renovation guide explores the complete renovation timeline so you can plan confidently and avoid costly delays.
1. Initial Consultation and Space Planning in a Renovation (1–2 Weeks)
Every successful home interior renovation starts with a solid foundation. During the first meeting, your interior designer will discuss your goals, lifestyle needs, design theme preferences, and budget to plan for your home renovation. The designer will also take site measurements and analyze your space to propose functional layout options.
Key Deliverables:
Site measurements
Client requirement brief
Proposed space plan
This stage sets the direction for the entire renovation project, so investing time here is essential when planning a renovation.
2. Design Concept Development (1 - 2 Weeks)
Once the space plan is approved, your interior designer will craft a design concept based on your preferred interior style—whether it’s modern, minimalist, Scandinavian, industrial, or eclectic. You’ll receive mood boards, material swatches, and 3D renderings to visualize how your renovated space will look.
Key Deliverables:
Thematic mood boards
Concept sketches and renderings
Design rationale and presentation
This phase ensures that your interior design vision aligns with practical and aesthetic goals.
3. Budgeting and Quotation Approval (1 Week)
With materials and scope finalized, your interior designer will provide a comprehensive quotation. This includes hacking works, masonry, electrical rewiring, carpentry, plumbing, and final styling. You’ll review and revise the quote before signing the agreement.
Key Deliverables:
Detailed quotation
Scope of work documentation
Project agreement and timeline
This stage defines your project scope and secures budget clarity for your interior renovation in Singapore.
Materials and Furniture Selection (1 - 2 Weeks)
Your designer will guide you through selecting key renovation finishes such as floor tiles, vinyl flooring, paint colors, cabinetry materials, lighting fixtures, and furniture. Choosing the right materials that match your interior design theme ensures design consistency.
Key Deliverables:
Tile and vinyl selection
Light and furniture specifications
Purchasing of sanitaryware
Procurement timeline planning
Material lead times may affect the renovation schedule, so timely decisions here are critical for a smooth renovation timeline.
5. Renovation Work Commencement (6–10 Weeks)
After approvals and permit clearances, renovation work begins. For minor works like kitchen renovation and bathroom upgrades, the timeline ranges from 3–5 weeks. Full-home renovations may take up to 10 weeks. Your designer will oversee site works, coordinate with subcontractors, and ensure quality control.
Stages Include:
Demolition and hacking
Tiling and masonry work
Electrical rewiring and plumbing
Carpentry and Doors fabrication and installation
Glass work and Aluminum works
Painting and detailing
Delays may arise due to permit processing, unforeseen site conditions, or material availability. Proper renovation planning helps reduce such risks.
6. Styling and Handover (1 Week)
The final stage involves moving in furniture, installing window treatments, arranging décor pieces, and completing soft furnishings. A final walkthrough will be conducted to resolve any defects.
Key Deliverables:
Final styling setup
Defect inspection and rectification
Official handover
Styling ensures your renovated space feels like home from day one.
Typical Renovation Timeline: 10–18 Weeks
From your first design consultation to the handover of your transformed home, a full home renovation managed by an interior designer in Singapore typically takes 3 to 4 months. The timeline may extend based on:
Project size and complexity
Custom-built elements
Permit approvals (e.g., HDB hacking permits)
Material sourcing and delivery
Proper timeline management and expert guidance from a renovation interior design firm make a significant difference in achieving timely results.
Final Thoughts
Hiring an interior designer ensures a streamlined, professionally managed renovation process. Understanding the full renovation timeline in Singapore—from space planning to concept development, material selection, and execution—gives you the clarity to manage expectations and make informed decisions.
Are you planning your dream home renovation? Let us help you bring your vision to life with expert interior design services and project management support. Contact us today to schedule your consultation!